01-19 – Phase 3 Expansion

Our Role

Rumble played a critical role in the success of the 01-19 – Phase 3 Expansion, working closely with engineering teams to develop detailed 3D modeling, pile layouts, Bills of Materials (BOMs), and fabrication isometric drawings (ISOs). Additionally, Rumble took the lead in driving overall project management on the mechanical side, ensuring seamless coordination, execution, and adherence to project timelines.

Key Developments

Estimated 650 Piles Installed to support new infrastructure.

Decommissioning & Removal of Aging Equipment:

  • Old oil treater
  • Old compressor package
  • Old booster compressor
  • Old flare stack
  • Old low- and high-pressure flare knockouts
  • Old dehydration unit (#1)
  • Old sales meter package
  • Old fuel gas separation package

Installation of New Infrastructure & Equipment:

  • (2) 2000 BBL oil tanks
  • (1) 2000 BBL water tank
  • Relocation of existing VRU and installation of an additional VRU
  • New 126-ft flare stack
  • New high- and low-pressure flare knockouts
  • New MCC (Motor Control Center) and generator packages
  • New larger oil treater
  • New inlet separator
  • New booster compressor
  • New sales compressors
  • New larger dehydration unit
  • New sales meter package
  • New fuel gas separation package
  • (2) New inlet barrels and 10” lines
  • (1) New 10” outlet barrel and line for new well pad lift gas
  • (1) New sales pipeline with barrel and full assembly
Features & Benefits

Optimized Facility Design:

Upgrading infrastructure to improve throughput and operational reliability.

Sustainability-Driven Enhancements:

Implementing carbon-reduction strategies and energy-efficient technologies.

Safety & Compliance Focus:

Meeting and exceeding industry safety regulations for a secure work environment.

Increased Production Efficiency:

Upgrading process systems to boost output while minimizing costs.

Scalability for Future Growth:

Designing infrastructure with adaptability in mind to support long-term development.

Project Info

Date: